Quantitative Methods Q55

0. The table below shows the after-tax cash flows of a project:
Year  0123456
Cash flow (€)    -50,00035,00025,00010,0002,0002,0003,000

The IRR of the project is closest to:

  • Option : A
  • Explanation : Using a financial calculator, compute IRR: CF0 = –50,000, CF1 = 35,000, CF2 = 25,000, CF3 = 10,000, CF4 = 2,000, CF5 = 2,000, and CF6 = 3,000, CPT IRR. The IRR is 27.05%.